|
Coventry
Airport introduced scheduled passenger flights in 2004 even though it
did not have planning permission for its new passenger terminal.
However, after a Public Inquiry, the Government granted retrospective
planning permission for an interim passenger facility.
Coventry Airport has since sought to expand its operations further but
the Government has rejected proposals for a much larger permanent terminal.
The airport challenged that decision in the High Court but was unsuccessful.
Because Coventry Airport is badly located in terms of public transport
access the overwhelming majority of passengers travel by car, increasing
congestion and carbon dioxide emissions on the road network.
The increased noise and impacts on air quality would be considerable.
We do not believe the airport is proposing good enough measures to contain
this.
Expansion would increase the impact on the countryside around the airport
and we continue to oppose it.
We specifically argued that the airport’s passenger throughput should
be capped at no more than 1 million per year. We also called for stronger
control over air freight activity at the airport.
However, events have now overtaken the planning process and Coventry is
no longer in use for passenger flights and its future is uncertain. You
can read more about the success of our campaign below.

Coventry
Airport finally accepts the answer ‘no’
After 6 years, 3
environmental impact assessments, 2 public inquiries and subsequent legal
appeals, Coventry Airport has finally accepted that it cannot develop
a new passenger terminal.
Scheduled passenger
flights started at Coventry in 2004 using a temporary building without
planning permission. The local planning authority took enforcement action
and this led to a public inquiry in 2005, at which CPRE teamed up with
the community group and a local councillor opposing airport expansion.
Before the outcome of this inquiry was known, a second inquiry started,
this time into a permanent passenger terminal many times the size of the
temporary building.
The local planning
authority didn’t object to the much larger terminal in the second
inquiry. Midway through, the Government announced its decision on the
first inquiry: although the temporary passenger terminal was judged unlawful,
planning permission was granted retrospectively. Despite this setback,
we pressed our case opposing expansion: among others, we showed increased
noise impact and a problem of getting to the airport situated at the end
of a 2km cul-de-sac. We argued that supposed mitigation measures were
not sufficient.
The inquiry dragged
on for seven months but eventually the Government decided the permanent
passenger terminal was not acceptable: the proposal did not comply with
sustainable development policies; there would be significant noise nuisance;
there were not sufficient benefits to outweigh environmental damage. But
Coventry Airport would not accept this rejection. They appealed to the
High Court. They lost, so they embarked on further appeals to the Appeal
Court. But finally in 2009 they accepted the inevitable: they could not
expand passenger flights.
We have now returned
to the position where there are no scheduled passenger flights from Coventry
Airport.
26.06.09
|